Martin Posted February 12, 2018 Report Share Posted February 12, 2018 Hi, can you split up the emergency lighting monthly testing in a large building in a similar way as to weekly fire alarm testing i.e. test each floor say each month so that after six months the whole building has been tested or do you have to test all emergency lights every month as we have about 300? Quote Link to comment Share on other sites More sharing options...
AnthonyB Posted February 12, 2018 Report Share Posted February 12, 2018 No, to comply with the maintenance standard it's all fittings. Quote Link to comment Share on other sites More sharing options...
Martin Posted February 13, 2018 Author Report Share Posted February 13, 2018 Many thanks. Quote Link to comment Share on other sites More sharing options...